HLSG Textile Care Services (TCS) - Laundry Plant Retrofit

Project Description
LDG served as the lead design consultant for the comprehensive retrofit of the existing laundry plant, tasked with modernizing the facility while maintaining full operational continuity. The scope included a complete integration of new technologies, replace obsolete systems and enhance safety and efficiency without disrupting daily production. LDG led the design effort from concept through final construction documents, coordinating closely with stakeholders to ensure all operational requirements were met. Special attention was given to phasing and sequencing to allow continuous operation during construction, minimizing downtime and maintaining throughput. In addition to their design responsibilities, LDG managed the equipment procurement process, identified and hired capable local/regional contractors/ engineers, code review and permitting with qualified Client’s A&E teams, project accounting and oversaw final commissioning and training
Project Highlights
LDG provided Strategic planning, design engineering, procurement and project management services for the retrofit of an existing laundry facility. The retrofit was executed in 3 phases with Monorail, Tunnel & Press and Dryer & Shuttle automation. Total work was completed in 10 days of plant production impact.
Utility reductions 38%
Equipment suppliers:
Washroom: Kannegiesser
Rail: Kannegiesser
Drying/shuttle system: Kannegiesser
Contractors:
Kannegiesser
Egan
Valor
LOCATION:
Rochester, MN
TASKS:
Preconstructon Services (Design,
Workflow, Engineering), Procurement
(RFP), Project Management Services
CLIENT TYPE:
Healthcare
PROJECT TYPE:
110,000 sqft Healthcare Laundry RETROFIT
ANNUAL POUNDS:
45M
VALUE:
$10.5M
Gallery




HLSG Textile Care Services (TCS) - Laundry Plant Retrofit
LDG served as the lead design consultant for the comprehensive retrofit of the existing laundry plant, tasked with modernizing the facility while maintaining full operational continuity. The scope included a complete integration of new technologies, replace obsolete systems and enhance safety and efficiency without disrupting daily production. LDG led the design effort from concept through final construction documents, coordinating closely with stakeholders to ensure all operational requirements were met. Special attention was given to phasing and sequencing to allow continuous operation during construction, minimizing downtime and maintaining throughput. In addition to their design responsibilities, LDG managed the equipment procurement process, identified and hired capable local/regional contractors/ engineers, code review and permitting with qualified Client’s A&E teams, project accounting and oversaw final commissioning and training
HLSG Textile Care Services (TCS) - Laundry Plant Retrofit
LDG served as the lead design consultant for the comprehensive retrofit of the existing laundry plant, tasked with modernizing the facility while maintaining full operational continuity. The scope included a complete integration of new technologies, replace obsolete systems and enhance safety and efficiency without disrupting daily production. LDG led the design effort from concept through final construction documents, coordinating closely with stakeholders to ensure all operational requirements were met. Special attention was given to phasing and sequencing to allow continuous operation during construction, minimizing downtime and maintaining throughput. In addition to their design responsibilities, LDG managed the equipment procurement process, identified and hired capable local/regional contractors/ engineers, code review and permitting with qualified Client’s A&E teams, project accounting and oversaw final commissioning and training
5940 S Rainbow Blvd
Las Vegas, NV
USA 89118
Head Office
Canadian Office
246 Stewart Green SW #1944
Calgary, Alberta Canada T3H 3C8
Head Office
5940 S Rainbow Blvd
Las Vegas, NV
USA 89118
Canadian Office
246 Stewart Green SW #1944
Calgary, Alberta Canada T3H 3C8